Kings Road Phase 3

Kings Road Phase 3

GCL are proud to have secured Kings Road Park Phase 3 at the former Gasworks site in Fulham which is worth in excess £38m. Substructure works have commenced on the first block with piling currently ongoing.

The Phase 3 package consists of forming a large basement (approx. 9,000m2) with some areas going to B-2 level which is located within an existing gas holder, a podium slab which covers the entire Phase 3 area and several RC Frame blocks ranging in height. There will be a total of 4 tower cranes installed on the phase which also forms part of the contract.

Inhouse capabilities will aid the construction of phase 3 with some innovative temporary works, core methodologies and precast elements being used throughout.

We look forward to working and delivering this fantastic development with St William’s team over the months ahead.