Skip to content
< All projects

Grand Union Phase 2

Location

Alperton

Services we provided

Concrete frames icon

Concrete frames

Demolition icon

Demolition

Tower crane icon

Tower cranes

Riverwall & Embankment Work Icon

Riverwall & Embankment Work

Ground works icon

Groundworks

Value

£23.1m

Description

Works at the well-known St George site in Wembley commenced in November 2021. Enabling works consisted of a large muck shift, piling mat and piling for 4no blocks ranging from 7 to 18 floors in height. 3no Tower Cranes from TCUK served the project throughout.  In-house designs such as temporary works, precast stairs and precast columns (PCUK) were a key part to the success of Phase 2. The early engagement with the design teams resulted in a large conversion rate from in-situ to precast for columns and stairs. The benefits of this resulted in less deliveries to site, programme certainty along with the tower cranes working a lot more efficiently on other elements of the build. Part of the works also consisted of the canal embankment upgrade which was formed alongside the ground works and frames. Our in-house technical and site teams worked closely with the Canal River Trust to get the designs and finished works approved through several meetings and workshops.

Construction features

  • 30,000m3 muck off site
  • 800 Piles Installed
  • 26,000m3 Concrete Poured
  • 3,200t Steel Fixed
  • 3no Cores RCS Jump Form
  • 1452no Pre-Cast Columns
  • 104no Pre-Cast Stairs
  • 3no Tower Cranes
  • Canal Embankment Upgrade